Pokhara Regional International Airport Project
Kaski, Pokhara
- Commercial Contract Agreement between CAAN and China CAMC Engineering Co. Ltd. On 22 May 2014.
- Loan Agreement between Governments of Nepal & Government of China on 21 March 2016.
- Subsidiary Loan Agreement between Government of Nepal & CAAN on 5 June 2016.
- Loan Effective letter dispatched by China Exim Bank from 31 May 2017.
- Letter to Proceed issued to China CAMC Engineering Co. Ltd. for Pokhara Regional International Airport Construction work on 11 July 2017.
- Contractor Started work on Site from 1 November 2017.
- Implementation Agreement between Governments of Nepal, CAAN & China Exim Bank on 25 February 2018.
Salient Features of PRIAP
- Runway : 2500m X 45m
- Parallel Taxiway : 900 m x 23 m
- Link Taxiway : 3 Nos.
A Link Taxiway : 142 m X 28.5 m
B Link Taxiway : 208.5 m X 34 m
C Link Taxiway : 208.5 m X 18 m
- Airport Periphery Road : 3 m wide
- Airport Approach Road : 20 m wide (4 lane)
- Apron
International & Domestic : 417m X 129m
Future Expansion : 150m X 152.5m
- ITB & DTB : (14643.76 square meter)
- Hangar : (6055.95 square meter)
- Control Tower : (1117.58 square meter)
- Rescue & Fire Fighting Facilities : CAT VIII including firefighting trucks & Ambulance
- Approach Light : ILS System precision approach CAT-I
1. Design Works
- Approval of Flight Procedure Design.
- Approval of Earthwork Drawing and Design.
- Approval of Airfield Working Drawing ( Airfield Layout, Pavement, Airport Drainage)
- Approval of Terminal Building Drawing ((Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed
- Approval of working drawing of Structure/Water Supply & Drainage / Electrical/Low Voltage) Completed
- Approval of working drawing of Navigation Lighting in Final Stage.
- Approval of working drawing of Communication, Navigation & Surveillance in Final Stage.
- Approval of working drawing of Hanger Building (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage Completed.
- Approval of working drawing of Ancillary Building- 12 Nos (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage completed
- Approval of Air Traffic Control (ATC) Tower Drawing (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
- Approval of Overhead Water Tank Drawing (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
- Navigation Aid Lighting 18m High Pole Light, Node and Foundation (Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
- HVAC System Design in Final Stage.
- Airport Access Road Design in Final Stage.
- DVOR/DME Design in Final Stage.
- Civil Construction Work
I) Latest Status of Airfield
A) Pavement work
- Runway completed.
- Apron Completed.
- Taxiway Completed.
- Hanger Apron- Cement Treated Base Completed
B) Airfield Lighting
- Secondary Conduit laying for runway completed.
- Secondary Conduit laying for taxiway completed.
- Installation of Transformer Box Completed.
C) Slab Culvert/ Irrigation canal Drainage Work
-100% completed.
D) Earthwork
- 95% completed.
II) Latest Status of Buildings work
- Terminal Building
- Foundation and Tie Beam Completed.
- RCC Column Casting & Steel Column Erection form Completed.
- Slab reinforcement and formworks ongoing.
- Hangar
- All Concrete Structure (Footing, Column Beam Slab) completed.
- Masonry works Completed.
- Concreting of parking area floor completed.
- Plaster work and Steel Structure erection on going.
-
- Sewage Station
- All Concrete Structure (Footing, Column, and Beam & Slab) completed.
- Block Masonry, plaster works and Structure Flooring completed.
- Waste Transfer Building
- All Concrete Structure (Footing, Column, Beam & Slab) completed.
- Block Masonry, plaster works and Structure Flooring completed.
- Fire rescue Station
- All Concrete Structure (Footing, Column, Beam & Slab) completed upto 2nd
- Block Masonry works and Structure Flooring completed.
- Plaster works ongoing.
- Special Vehicle Garage
- All Concrete Structure (Footing, Column, Beam & Slab) completed.
- Block Masonry works and Structure Flooring completed.
- Plaster works ongoing.
- Cargo building
- All Concrete Structure (Footing, Column, Beam & Slab) completed.
- Block Masonry works
- Plaster works ongoing.
- Custom and immigration building
- All Concrete Structure (Footing, Column, Beam & Slab) completed up to 4th
- Block Works in 1st, 2nd and 3rd floor completed and ongoing in 4th floor
- Plastering ongoing.
- Integrated Office Building
- Footing ,tie beam and first floor slab completed
- Column rebar for second floor ongoing.
- Block works in 1st floor ongoing.
- Water Supply Station
- Concrete works in Pump house and Water Tanks completed.
- Block work for pump house ongoing.
- Reinforcements and formworks in Water Tower ongoing.
- Fire Rescue Watch Tower
- All Concrete Structure (Footing, Column, Beam & Slab) completed up to 4th
- Central Substation
- All Concrete Structure (Footing, Column, Beam & Slab) completed.
- Plaster works ongoing
- Lighting substation
- All Concrete Structure (Footing, Column, Beam & Slab) completed.
- Block works ongoing.
14.1 ATC Complex Building
- All Concrete Structure (Footing, Column, Beam & Slab) completed up to 3rd floor
- Block work Completed & Plastering ongoing.
14.2 ATC Control Tower
- Concreting for the 5th floor shear wall completed
- Rebar and formworks for the 6th floor shear wall ongoing.
- Airport Gate
- Concreting of Tie beam completed.
- Concreting of beam, slab and column completed.
- Block work ongoing
Financial Status
- Land Acquisition expenditure (except Periphery Road) till date – NPR 3 billion
- Advance Payment made to CHINA CAMC Engineering Co. Ltd of USD 30.95 Million
- Total IPC Running bill payment made to CHINA CAMC Engineering Co. Ltd till date – USD 77.411 Million (Approx. NPR 8.51 billion) with VAT
- Total IPC Running bill payment made to Design Review & Supervision Consultant Running Bill till the date – NPR 87.53 million.
- Land Acquisition expenditure for Outer periphery Road till date – NPR 510 million.
- Overall Financial Progress of construction work 31.73%.
Physical Status
- Overall 50% of whole Project.
IPC 10 USD 23.173 m
2.55 BILLION with VAT
100.584 (11.06 billion)
Financial progress overall (41.22%)