कार्यक्रम : 23_ २३ DG-CAAN पोखरा क्षेत्रीय अन्तर्राष्ट्रिय विमानस्थलको हालको निर्माण गति कायम राख्दै निर्धारित समयअघि नै सम्पन्न गर्ने व्यवस्था मिलाउने । DG-CAAN

मिति : 2019-11-10

जिम्मेवार निकाय: CAAN- HEAD OFFICE

जानकारी :

Pokhara Regional International Airport Project

Kaski, Pokhara

 

  • Commercial Contract Agreement between CAAN and China CAMC Engineering Co. Ltd. On 22 May 2014.
  • Loan Agreement between Governments of Nepal & Government of China on 21 March 2016.
  • Subsidiary Loan Agreement between Government of Nepal & CAAN on 5 June 2016.
  • Loan Effective letter dispatched by China Exim Bank from 31 May 2017.
  • Letter to Proceed issued to China CAMC Engineering Co. Ltd. for Pokhara Regional International Airport Construction work on 11 July 2017.
  • Contractor Started work on Site from 1 November 2017.
  • Implementation Agreement between Governments of Nepal, CAAN & China Exim Bank on 25 February 2018.

Salient Features of PRIAP

  • Runway                     :     2500m X 45m
  • Parallel Taxiway          :     900 m x 23 m
  • Link Taxiway              :     3 Nos.

   A Link Taxiway                                :     142 m X 28.5 m

   B Link Taxiway                                :     208.5 m X 34 m

   C Link Taxiway                                :     208.5 m X 18 m

  • Airport Periphery Road  :     3 m wide          
  • Airport Approach Road  :  20 m wide (4 lane)
  • Apron

            International  & Domestic                 :      417m X 129m

            Future Expansion                            :      150m X 152.5m

  • ITB & DTB                :     (14643.76 square meter)
  • Hangar :     (6055.95 square meter)
  • Control Tower    :     (1117.58 square meter)
  • Rescue & Fire Fighting Facilities : CAT VIII including firefighting trucks & Ambulance
  • Approach Light :     ILS System precision approach CAT-I

1. Design Works 

  • Approval of Flight Procedure Design.
  • Approval of Earthwork Drawing and Design.
  • Approval of Airfield Working Drawing ( Airfield Layout, Pavement, Airport Drainage)
  • Approval of Terminal Building Drawing ((Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed
  • Approval of working drawing of Structure/Water Supply & Drainage / Electrical/Low Voltage) Completed
  • Approval of working drawing of Navigation Lighting in Final Stage.
  • Approval of working drawing of Communication, Navigation & Surveillance in Final Stage.
  • Approval of working drawing of Hanger Building (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage Completed.
  • Approval of working drawing of Ancillary Building- 12 Nos (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage completed
  • Approval of Air Traffic Control (ATC) Tower Drawing (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
  • Approval of Overhead Water Tank Drawing (Architecture, Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
  • Navigation Aid Lighting 18m High Pole Light, Node and Foundation (Structure/Water Supply & Drainage / Electrical/Low Voltage) completed.
  • HVAC System Design in Final Stage.
  • Airport Access Road Design in Final Stage.
  • DVOR/DME Design in Final Stage.

 

  1. Civil Construction Work

I) Latest Status of Airfield

A) Pavement work

- Runway completed.

- Apron Completed.

- Taxiway Completed.

- Hanger Apron- Cement Treated Base Completed

B) Airfield Lighting

            - Secondary Conduit laying for runway completed.

           - Secondary Conduit laying for taxiway completed.

           - Installation of Transformer Box Completed.

 

C) Slab Culvert/ Irrigation canal Drainage Work

               -100% completed.

D) Earthwork

             - 95% completed.

 

II) Latest Status of Buildings work

  1. Terminal Building
  • Foundation and Tie Beam Completed.
  • RCC Column Casting & Steel Column Erection form Completed.
  • Slab reinforcement and formworks ongoing.
  1. Hangar
  • All Concrete Structure (Footing, Column Beam Slab) completed.
  • Masonry works Completed.
  • Concreting of parking area floor completed.
  • Plaster work and Steel Structure erection on going.
  •  
  1. Sewage Station
  • All Concrete Structure (Footing, Column, and Beam & Slab) completed.
  • Block Masonry, plaster works and Structure Flooring completed.
  1. Waste Transfer Building
  • All Concrete Structure (Footing, Column, Beam & Slab) completed.
  • Block Masonry, plaster works and Structure Flooring completed.
  1. Fire rescue Station
  • All Concrete Structure (Footing, Column, Beam & Slab) completed upto 2nd
  • Block Masonry works and Structure Flooring completed.
  • Plaster works ongoing.
  1. Special Vehicle Garage
  • All Concrete Structure (Footing, Column, Beam & Slab) completed.
  • Block Masonry works and Structure Flooring completed.
  • Plaster works ongoing.
  1. Cargo building
  • All Concrete Structure (Footing, Column, Beam & Slab) completed.
  • Block Masonry works
  • Plaster works ongoing.
  1. Custom and immigration building
  • All Concrete Structure (Footing, Column, Beam & Slab) completed up to 4th
  • Block Works in 1st, 2nd and 3rd floor completed and ongoing in 4th floor
  • Plastering ongoing.
  1. Integrated Office Building
  • Footing ,tie beam and first floor slab completed
  • Column rebar for second floor ongoing.
  • Block works in 1st floor ongoing.
  1. Water Supply Station
  • Concrete works in Pump house and Water Tanks completed.
  • Block work for pump house ongoing.
  • Reinforcements and formworks in Water Tower ongoing.
  1. Fire Rescue Watch Tower
  • All Concrete Structure (Footing, Column, Beam & Slab) completed up to 4th
  1. Central Substation
  • All Concrete Structure (Footing, Column, Beam & Slab) completed.
  • Plaster works ongoing
  1. Lighting substation
  • All Concrete Structure (Footing, Column, Beam & Slab) completed.
  • Block works ongoing.

14.1 ATC Complex Building

  • All Concrete Structure (Footing, Column, Beam & Slab) completed up to 3rd floor
  • Block work Completed & Plastering ongoing.

14.2 ATC Control Tower        

  • Concreting for the 5th floor shear wall completed
  • Rebar and formworks for the 6th floor shear wall ongoing.
  1. Airport Gate
  • Concreting of Tie beam completed.
  • Concreting of beam, slab and column completed.
  • Block work ongoing

Financial Status

  • Land Acquisition expenditure (except Periphery Road) till date – NPR 3 billion 
  • Advance Payment made to CHINA CAMC Engineering Co. Ltd of USD 30.95 Million
  • Total IPC Running bill payment made to CHINA CAMC Engineering Co. Ltd till date – USD 77.411 Million (Approx. NPR 8.51 billion) with VAT
  • Total IPC Running bill payment made to Design Review & Supervision Consultant Running Bill till the date – NPR 87.53 million.
  • Land Acquisition expenditure for Outer periphery Road till date – NPR 510 million.
  • Overall Financial Progress of construction work 31.73%.

Physical Status

  • Overall 50% of whole Project.

IPC 10 USD 23.173 m

2.55 BILLION with VAT

100.584 (11.06 billion)

Financial progress overall (41.22%)