कार्यक्रम : 57_ ५७ EC-NAC MoCTCA नेपाल वायु सेवा निगमका सबै विमानहरु सञ्चालनमा ल्याउने । ३ महिना EC-NAC

मिति : 2019-12-08

जिम्मेवार निकाय: NAC_OFFICE

जानकारी :

DHC6 300 (9N-ABX)

i.                    wing life extension work in progress

ii.                 Arrangement of required spares in process

Tentative release date- 45 days after completion of wing life extension

wing life extensiondue,TAWS installation due, C of A due

Y12E (9NAKS)

i.                    Engine installation in process

ii.                  3 years check started

iii.                Required spares ordered

Tentative release date- February 2020

Some spares not available, C of A due

Y12E (9NAKT)

3 years check is in progress

Tentative release date- Mid December  2019

3 years check due

Y12E (9NAKU)

Spares arrangement in process

Tentative release date- February 2020

Few spares (portable oxygen bottle, multifunctional display, CVR) not available in stock

MA60 (9NAKQ)

Arrangement of required spares in in progress in coordination with AVIC. APU robbed to service AKR

Tentative release date- January 2020

OEM MRO Approval pending, Few spares installation remaining